About this project

Upgrade of up to 13 pump stations and one CSO Pump Station. 12/18/2020 The purpose of the Amendment wass to decrease the City of Nashuas existing CWSRF Loan by $3,615,000, to $4,885,000, the amount necessary to complete phase 1 of the Pump Station Upgrades project. The overall project was split into two phases. This phase of the project is approaching completion and repayments are anticipated to begin in August.