Winnipesaukee River Basin ProgramClean Water Infrastructure

Franklin, Merrimack County · Approved July 27, 2022

the WRBP facility
Photo: NH Department of Environmental Services

About this project

Total project cost: $1,530,000 ARPA Grant: $459,000 CWSRF Loan: $1,071,000 Approved: July 27, 2022 The WRBP will use the grant and loan funding to replace 10 of the original emergency back-up generators at WRBP pump stations that are past their remaining useful life and are increasingly problematic to repair and maintain.