Unofficial prototype by NovaHawk Labs, compiled from public NHDES and EPA records. Not an NHDES website. Covers 1191 projects, 2015 to 2026. How this was built

NH Water Infrastructure FundingProject-level funding by community, county and legislative district

Wastewater and clean water

Winnipesaukee River Basin ProjectCentralized Wastewater Treatment - Secondary Treatment

Franklin, Merrimack County · Approved March 9, 2022

About this project

The project will include upgrades to solids handling equipment and controls throughout the Wastewater Treatment Plant which include improved primary digester mixing, implementation of a new process to thicken waste activated sludge, biogas management and digester and building heating systems. These improvements will enable the facility to meet increased demands on the Franklin WWTP and continue to meet more stringent state and federal permit requirements, improve treatment facility operations, and reduce energy and operating costs associated with solids handling processes.

Location