Winnipesaukee River Basin ProjectCentralized Wastewater Treatment - Secondary Treatment
Franklin, Merrimack County · Approved March 9, 2022
About this project
The project will include upgrades to solids handling equipment and controls throughout the Wastewater Treatment Plant which include improved primary digester mixing, implementation of a new process to thicken waste activated sludge, biogas management and digester and building heating systems. These improvements will enable the facility to meet increased demands on the Franklin WWTP and continue to meet more stringent state and federal permit requirements, improve treatment facility operations, and reduce energy and operating costs associated with solids handling processes.