Town of MerrimackCentralized Wastewater Treatment - Secondary Treatment

Merrimack, Hillsborough County · Approved October 4, 2022

About this project

The initial project includes technical services for final design including topographic, wetlands, geotechnical, and asbestos/lead surveys, a radio path cell feasibility study and value engineering in preparation for the construction phase scheduled to start September of 2020. The purpose of the Amendment is to fund construction of the WWTF Phase III and Pump Station Upgrades project. The amendment will primarily fund the construction of a new screenings facility and an upgrade of two main wastewater pumping stations.

Location