City of PortsmouthCentralized Wastewater Treatment - Advanced Treatment
Portsmouth, Rockingham County · Approved June 27, 2022
About this project
The project involves demolition of several buildings and construction of new facilities including a new headworks building; a new gravity thickener; replacement of the existing Administration Building with a new Solids Building; a new two-stage Biological Aerated Filter (BAF) system; demolition of the first floor of the existing Solids Processing Building and replacement with a new first floor superstructure of the Operations/Lab Building on the foundation of the former Sludge Processing Building, and associated utility and site improvements within the fenced facility. Offsite improvements include a new water main and a new electric service from the pool to the WWTF with associated roadway repairs. Construction is anticipated to take approximately three to four years and the facility will be operational throughout the duration of construction.