Town of SeabrookCritical Flood Risk Infrastructure

Seabrook, Rockingham County · Approved November 22, 2022

About this project

ARPA Grant: $1,050,200 Approved: November 22, 2022 The Town of Seabrook will use the funds to for implementation of adaptation solutions to increase flood resilience of the Seabrook Wastewater Treatment Facility. These solutions include waterproofing and raising the entrances of metering vaults, raising the entrance of the influent screw pump vault, installing deployable barriers to protect critical process buildings, and increasing the resiliency of control systems by upgrading hardware and software.